Hacker Newsnew | past | comments | ask | show | jobs | submitlogin

That’s interesting, we visited many datacenters across Skåne and none of them said anything higher than T2 is possible due to the single power grid.

Does Bahnhof and Tele2 know about your stations?



Just curious what you mean by independent power feed. If you mean fed by two separate power plants, you are right, but I don’t see how that would be possible in any country.

My next work assignment literally starting in a week is building a high voltage substation for a data center(customer is well known on HN) so that’s why I’m curious




Guidelines | FAQ | Lists | API | Security | Legal | Apply to YC | Contact

Search: